Friday, November 27, 2009
Thursday, November 26, 2009
(Historical) Canadian PM Harper in Yukon September 2009 Siku News
Mayo Power project upgrade - transmission to link two Yukon Electric Transmission Systems
Why put this in AED? The interconnection of Whitehorse to Dawson, Yukon means that roughly 250 plus miles separates an interconnection between Dawson and Delta Junction, Alaska. On the southern end of Yukon's power grid, a link from Carcross Jct to Skagway's Goat Lake project is roughly 50 miles. So, an interconnection of Southeast Alaska through Yukon to the Railbelt isn't that far fetched. Nothing is understood to be planned by either Yukon Energy nor the Alaska Energy Authority, however an interconnection between the Alaska Railbelt and Southeast isn't insurmountable, nor farfetched either.
Why put this in AED? The interconnection of Whitehorse to Dawson, Yukon means that roughly 250 plus miles separates an interconnection between Dawson and Delta Junction, Alaska. On the southern end of Yukon's power grid, a link from Carcross Jct to Skagway's Goat Lake project is roughly 50 miles. So, an interconnection of Southeast Alaska through Yukon to the Railbelt isn't that far fetched. Nothing is understood to be planned by either Yukon Energy nor the Alaska Energy Authority, however an interconnection between the Alaska Railbelt and Southeast isn't insurmountable, nor farfetched either.
Delta Wind Farm Online, Ready to add a Generator - Alaska Journal of Commerce, Sept 2009
Click to read story
By Rob Stapleton
Alaska Journal of Commerce
The first of several wind generators erected by Alaska Environmental Power, LLC stands on a knoll 120 feet above the Tanana Valley floor near Delta Junction. This 100-kilowatt generator is now providing power into Golden Valley Electric Associations grid. The Fairbanks company will erect a second 900-kilowatt wind generator that will go online in October at the same location with plans to create a 15-megawatt farm in the future. Photo/Rob Stapleton/AJOC
Two years and a lot of hard work later, a wind farm that now generates electricity into the Golden Valley Electric Association grid is taking shape on a knoll near Delta Junction.
Alaska Environmental Power, LLC has one wind generator up and running, and has set the foundation for another. The generator site is northwest of Delta.
By Rob Stapleton
Alaska Journal of Commerce
The first of several wind generators erected by Alaska Environmental Power, LLC stands on a knoll 120 feet above the Tanana Valley floor near Delta Junction. This 100-kilowatt generator is now providing power into Golden Valley Electric Associations grid. The Fairbanks company will erect a second 900-kilowatt wind generator that will go online in October at the same location with plans to create a 15-megawatt farm in the future. Photo/Rob Stapleton/AJOC
Two years and a lot of hard work later, a wind farm that now generates electricity into the Golden Valley Electric Association grid is taking shape on a knoll near Delta Junction.
Alaska Environmental Power, LLC has one wind generator up and running, and has set the foundation for another. The generator site is northwest of Delta.
Bullfrog Power News
Bullfrog Power News
I thought to put some news from our neighbors just next door. What is being done in other jurisdictions regarding renewable energy only miles away from Alaska.
I thought to put some news from our neighbors just next door. What is being done in other jurisdictions regarding renewable energy only miles away from Alaska.
Policies to Support Increased Renewable Energy to be Developed by Yukon Government, Whitehorse, YK Nov 25, 2009
Click here for press release
A public consultation for developing Yukon policies for independent power production (IPP) and net metering was announced today by Minister of Energy, Mines and Resources Archie Lang.
“As a key initiative of Yukon’s Energy Strategy, these policies will encourage the development of new small scale sources of renewable energy to help meet our future energy needs while limiting green house gas emissions and improving electrical system reliability,” Lang said.
A public consultation for developing Yukon policies for independent power production (IPP) and net metering was announced today by Minister of Energy, Mines and Resources Archie Lang.
“As a key initiative of Yukon’s Energy Strategy, these policies will encourage the development of new small scale sources of renewable energy to help meet our future energy needs while limiting green house gas emissions and improving electrical system reliability,” Lang said.
Tuesday, November 24, 2009
Major Step for Wind Power in the Southeast
Major Step for Wind Power in the Southeast
Posted using ShareThis
No, this isn't Southeast Alaska, but it could be.
Posted using ShareThis
No, this isn't Southeast Alaska, but it could be.
Monday, November 23, 2009
Saturday, November 21, 2009
Friday, November 20, 2009
A Sea of Potential in Alaska « Mendo Coast Current
A Sea of Potential in Alaska « Mendo Coast Current An older, but relevant article by Brian Yannity on the ocean energy potential off Alaska's coast
Thursday, November 19, 2009
Wednesday, November 18, 2009
News :: Radio Kenai | radiokenai.com | KSRM, KWHQ, KKIS, KSLD
News :: Radio Kenai | radiokenai.com | KSRM, KWHQ, KKIS, KSLD DNR's Irwin says a spur line is more economical than a bullet line
Fairbanks Daily News-Miner - Officials defend gas line efforts
Fairbanks Daily News-Miner - Officials defend gas line efforts FAIRBANKS — State officials said Tuesday night that efforts to spur construction of a massive natural gas pipeline are on schedule despite skepticism from critics and some lawmakers.
The plan, pitched by former Gov. Sarah Palin under the Alaska Gasline Inducement Act, is projected to have drawn $150 million in investments from the team of TransCanada and Exxon Mobil by mid-summer, according to an October progress report.
The plan, pitched by former Gov. Sarah Palin under the Alaska Gasline Inducement Act, is projected to have drawn $150 million in investments from the team of TransCanada and Exxon Mobil by mid-summer, according to an October progress report.
Alaskans must build their own gas pipeline: Compass | adn.com
Alaskans must build their own gas pipeline: Compass | adn.com
This was an opinion by an Alaska Gubernatorial Candidate on an Alaskan Natural Gas Pipeline.
This was an opinion by an Alaska Gubernatorial Candidate on an Alaskan Natural Gas Pipeline.
Tuesday, November 17, 2009
SitNews - Opinion/Letter: Heating and power generation By A.M.Johnson
SitNews - Opinion/Letter: Heating and power generation By A.M.Johnson Energy News out of Ketchikan? One Citizen's Viewpoint
Prince George Free Press - First cargo jet customer arrives at P.G. airport
Prince George Free Press - First cargo jet customer arrives at P.G. airport
The first Boeing 747 cargo aircraft to land at Prince George Airport touched down at approximately 8:15 a.m. Tuesday morning.
The Southern Air Inc. flight arrived from Anchorage, changed flight crews, took on approximately 130,000L of fuel and departed for Caracas, Venezuela.
The first Boeing 747 cargo aircraft to land at Prince George Airport touched down at approximately 8:15 a.m. Tuesday morning.
The Southern Air Inc. flight arrived from Anchorage, changed flight crews, took on approximately 130,000L of fuel and departed for Caracas, Venezuela.
Monday, November 16, 2009
International Water Power and Dam Construction
International Water Power and Dam Construction Brian Yanity presents a review of regional hydro power development strategies involving proposed international transmission lines connecting the US state of Alaska and Canada
Sunday, November 15, 2009
Syntroleum Corp. tops list of state’s best companies | NewsOK.com
Syntroleum Corp. tops list of state’s best companies | NewsOK.com
Interesting if not exactly something we can use here.
Interesting if not exactly something we can use here.
Saturday, November 14, 2009
Friday, November 13, 2009
Energy plan calls for unifying (Railbelt) electric utilities
Energy plan calls for unifying electric utilities There is some commentary published which relate to Southeast Alaska and why a different transmission organization ought to be considered.
AltaGas short-circuits BC Hydro
AltaGas short-circuits BC Hydro This action by AltaGas, the owner of nearby BC run-of-river hydro project proposals, would short circuit the process to get the east of Wrangell Northwest Transmission Line moving in an expedited manner. It makes a connection to Southeast Alaska even more tangible.
Tuesday, November 10, 2009
Monday, November 9, 2009
Man of the North - BC Business Online
Click here to read story As a youth, Tom Albanese fled a small industrial New Jersey town for Alaska. Albanese, now 50, is the first American CEO of the venerable London-based mining giant Rio Tinto PLC (RTP-N), which last year took over Alcan Inc. in a $38-billion deal. He went to university in Fairbanks, Alaska, for degrees in mineral economics and mining engineering.
Thursday, November 5, 2009
Tuesday, November 3, 2009
"Make liquid fuels from Alaska's Natural Gas" Richard Peterson, Alaska Natural Gas-to-Liquids, Tim Bradner, Alaska Journal of Commerce
Click on story link in left hand column.
Monday, November 2, 2009
Sunday, November 1, 2009
Subscribe to:
Posts (Atom)